Project Scope
Addition of two 70,000 BBL IFR crude oil storage tanks at the Hess Tioga Rail Loading facility. Civil, mechanical, and electrical engineering design, programming, and commissioning. Project included piping, electrical, instrumentation, automation, and fire water and foam systems.
- Project Management
- HAZOP/PHA
- Mechanical Engineering
- Civil/Structural Engineering
- E&I Engineering
- Construction Support and Inspection
- Programming, Startup, and Commissioning
Notable Accomplishments & Challenges
Upgraded existing fire systems and seamlessly integrated upgraded automation and control systems into existing panels.